Lands
31 Project(s)
Project NameStatusYearSub CountyWardBudget (Ksh)
Acquisition of land for PWDs Complete 2019/2020 Turkana Central Kalokol 4,500,000
Dumpsite in Kalokol Stalled 2016/2017 Turkana Central Kalokol 3,600,000
Installation of solar streetlights in kaeris Complete 2019/2020 Turkana North Kaeris 13,000,000
Kaaruko Dispensary (Solar PV Inst) Complete 2016/2017 Turkana East Katilia 7,102,000
Kainuk Dump site Complete 2016/2017 Aroo Lobokat 3,750,000
Kakuma Street Lights Complete 2014/2015 Turkana West Kakuma 19,000,000
Kalokol Public Toilets Complete 2015/2016 Turkana Central Kalokol 4,500,000
Kapedo street lights Complete 2016/2017 Suguta Kapedo/ Napeitom 7,102,000
Kapelbok primary school(Solar PV installation Complete 2016/2017 Aroo Kaputir 14,000,000
Katilu dump site Stalled 2016/2017 Aroo Katilu 3,450,000
Katilu street lights Complete 2015/2016 Aroo Katilu 9,938,068
Kokoriok Pri. School ( Solar PV Inst) Complete 2016/2017 Turkana East Katilia 7,102,000
Letea primary (Solar installation) Complete 2015/2016 Turkana West Letea 9,938,068
Loarengak Girls Pri. School(Solar PV inst) Complete 2016/2017 Turkana North Lakezone 7,102,000
Loarengak Street Lights Complete 2016/2017 Turkana North Lakezone 9,431,760
Lokori Dump site Ongoing 2016/2017 Turkana East Lokori/Kochodin 3,750,000
Lomil primary school solar panel PV system installation Complete 2016/2017 Loima Turkwel 3,600,000
Lopeduru Health Centre (Solar PV inst) Complete 2016/2017 Turkana East Katilia 7,102,000
Loroo Dispensary Solar panel PV installation system Complete 2016/2017 Loima Turkwel 3,600,000
Maintainance of Solar Streetlight in Lowarengak Not Started 2019/2020 Turkana North Lakezone 7,000,000
Showing 20 of 31 project(s) | Page 1 of 2